Skip to content
Cecil-Katoomba-18-1024x683

PROJECT

Cecil Guesthouse

Sewer Works

CLIENT

Cecil Guesthouse

SERVICE

Sewer Works

LOCATION
Katoomba
TIMELINE
August 2022

PROJECT INFORMATION

Cecil Guesthouse contacted our team to assist with the repairs of the sewer connection at the mains in the roadway and the pipework from the property to the sewer main junction

jetter-banner

OBJECTIVES & PRIORITIES

objectives_fit for purpose
Fit for Purpose
(compliant)
objectives_water reduction
Water
Reduction
objectives_quality workmanship
Quality
Workmanship
objectives_fast response
Fast Response
Deadlines

SCOPE OF WORKS

  • Detection of repairs required
  • Installation of bladder to ensure water couldn't flow into BT while works were being completed.
  • Set up and the installation of IMS robotic cutter to grind back concrete residue in sewer system.
  •  Carried out pipe relining preparation works to sewer including jet blasting and sanding, to create clean pipework for relining to take place
  • Installation of pipe relining
  • Testing and commissioning

KEY ACHIEVEMENTS

  • Minimal disruption to residents
  • Completed project on time and within budget
  • Worked closely with site manager to schedule all works
cdv_photo_304 (1)

RECENT PROJECTS

Let's chat about your next project or ongoing maintenance requirements

Schedule a Meeting