PROJECT

Anglicare

Replacement of sewer service damaged by tree roots

CLIENT
Anglicare
SERVICE

Sewer Replacement

LOCATION
Hopetoun RL, Castle Hill
TIMELINE
2022

PROJECT INFORMATION

Anglicare approached our team to address a pressing issue: the replacement of a sewer service damaged by tree roots. This problem posed concerns for health, safety, and operational disruption. The project's scope involved assessment, repair, and replacement of damaged sections with a focus on preventive measures. The expected outcome was the restoration of full sewer service functionality, ensuring the well-being of Anglicare's residents and the integrity of their property. 

cdv_photo_027 (3)

OBJECTIVES & PRIORITIES

objectives_fit for purpose
Fit for Purpose
(compliant)
objectives_cost savings
Cost
Savings
objectives_quality workmanship
Quality
Workmanship
objectives_fast response
Tight
Deadlines

SCOPE OF WORKS

  • Conducted a comprehensive on-site risk assessment to ensure the safety of personnel and the project environment.
  • Implemented an exclusion zone with temporary fencing to safeguard the work area and prevent unauthorized access.
  • Carried out precise service locating to identify and avoid potential underground services within the excavation area.
  • Employed mechanical excavation methods to dig a trench measuring 22m x 1m - 1.5m deep efficiently.
  • Removed and replaced 22m of 100mm earthenware pipework with new 100mm PVC pipework to enhance sewer system performance.
  • Seamlessly connected three existing junctions to the new sewer line, ensuring optimal functionality.
  • Supplied and installed two inspection openings raised to ground level, facilitating easy maintenance and monitoring.
  • Backfilled the pipework with suitable materials and filled the trench with existing spoil, ensuring structural integrity.
  • Conducted a thorough cleanup of the project site, leaving no debris or safety hazards behind.
  • Provided a 3m skip bin for efficient removal of project-related waste materials.
  • Supplied a 5-ton excavator for the project's duration, supporting excavation and construction activities.
  • Replaced existing turf to restore the site's appearance and functionality.

KEY ACHIEVEMENTS

  • Successful risk assessment and establishment of a secure work zone ensured safety throughout the project.
  • Minimal disruption to residents.
  • Mechanical excavation and replacement of damaged pipework with PVC improved sewer system reliability.
  • Three existing junctions seamlessly connected to the new sewer line for smooth functionality.
  • Thorough cleaning, proper backfilling, and waste management left the work area pristine.
  • Turf relay enhanced the site's appearance and functionality, delivering a complete project.